Istanbul Urban Renewal 2026: "Half on Us" Support and the Process

Serdar Savaş6 min readLast updated: September 23, 2026
Istanbul Urban Renewal 2026: "Half on Us" Support and the Process

1.5 million at-risk homes, the "Half on Us" grant-and-loan package valid until 31 December 2026, and the construction-contracting model: how to start urban renewal in Istanbul this autumn.

As of September 2026, Istanbul is estimated to have roughly 1.5 million at-risk homes. Since 2012, 1.27 million units have entered the renewal programme, yet most of the pre-1999 building stock is still standing. What makes this autumn different is the "Half on Us" (Yarısı Bizden) campaign deadline: 31 December 2026 for the risk assessment report. The decision window for property owners is closing.

This guide brings together the current support amounts, the districts where activity is concentrated, the difference between the flat-for-land and contracting models, and the full path from risk assessment to occupancy permit.

"Half on Us" 2026: Support Items and Conditions

The Ministry of Environment, Urbanisation and Climate Change runs this campaign for Istanbul only. Owners who demolish and rebuild an at-risk building receive a grant, a loan and a relocation payment together. The 2026 figures:

Support itemPer dwelling (TRY)Note
Grant875,000Non-repayable
Loan875,000Repayment starts 2 years after the permit, 10-year term, first year interest-free
Relocation support125,000One-off
Total1,875,000Per independent unit
Commercial unit grant437,500Shops and offices

The core condition is a risk assessment completed by a licensed institution before 31 December 2026. A simple-majority decision of the owners, then design and permit, follow. Monthly rent support for Istanbul in 2026 was announced at TRY 18,000–21,000.

Districts Leading in 2026

  • Avcılar, Küçükçekmece, Bahçelievler, Bağcılar, Güngören — pre-1999, weak ground conditions, dense apartment stock.
  • Zeytinburnu — among the districts with the highest renewal potential; block-based schemes are gaining ground.
  • Kadıköy, Maltepe, Kartal — high land values on the Asian side; the most intense plot-by-plot renewal.

Where land values are high, developers still offer flat-for-land deals. In the western districts of the European side, many buildings do not work economically on that basis. The "Half on Us" package was designed precisely for this second group.

The February 2026 Regulatory Update

A regulation amendment published on 4 February 2026 updated the timelines for assessment, evacuation and owner decisions under Law No. 6306. In practice, waiting periods after a risk decision are shorter and undecided owners have less room to block the process. Confirm the current text with the Ministry before applying.

Flat-for-Land or Construction Contracting?

With grant and loan flowing directly to the owners, building on a fixed price per square metre while keeping the full land share becomes affordable. We explain this in detail in our article on the construction-contracting alternative to flat-for-land.

CriterionFlat-for-landContracting + Half on Us
Land sharePart goes to the developerStays fully with the owners
CostHidden in lost unitsPer m², fixed in the contract
FinancingDeveloperGrant + loan + owner contribution
Quality controlDeveloperOwners and independent supervision

Savaş Grup's urban renewal under the construction-contracting model is built for that second column: assessment, design, permits and construction under one contract with transparent cost.

The Cost of Waiting: What TurkStat Says

According to the July 2026 Construction Cost Index released in September, costs rose 28.33% year on year; labour (30.51%) outpaced materials (27.13%). A project delayed by a year needs roughly a quarter more budget for the same scope; for an 80-unit building that difference erodes a large part of the grant. Our construction cost guide explains which items drive the cost.

Sample Budget: 80-Unit Building

ItemCalculationAmount (TRY)
Grant80 × 875,00070,000,000
Loan80 × 875,00070,000,000
Relocation80 × 125,00010,000,000
Total public support150,000,000

The total construction cost and the owners' contribution vary from building to building with storeys, unit sizes, ground conditions and finish level — which is why we prepare a separate calculation for each building instead of quoting a generic price per m². Use the "Half on Us" support calculator to see your building's total public support right away, then request a free pre-feasibility and quotation.

Step by Step (2026)

  1. Risk assessment — licensed institution, before 31 December 2026; approved by the provincial directorate.
  2. Owners' decision — simple majority for demolition and rebuild; choice of contractor.
  3. "Half on Us" application — via e-Government or the provincial directorate.
  4. Design and permit — architectural and structural design, soil survey, municipal permit (2–4 months).
  5. Evacuation and demolition — rent support starts; demolition and excavation (1 month).
  6. Construction — shell and finishes, 12–18 months; progress-based payments.
  7. Occupancy permit — title update and handover.

If the performance analysis concludes that demolition is not required, building strengthening should be considered — but note that "Half on Us" only funds demolition and rebuild.

Other Metropolitan Areas

"Half on Us" is specific to Istanbul. For Ankara and İzmir, the Ministry's general loan and rent-support programmes and local schemes apply; we have prepared separate guides for both cities.

Urban Renewal in Istanbul with Savaş Grup

With more than 27 years of contracting experience, we run the entire process on both sides of Istanbul — from risk assessment to turnkey delivery — under a single contract. We brief owners' meetings free of charge, calculate the grant-and-loan balance for the specific building and sign at a fixed price per square metre. To make the December 2026 deadline, start the assessment today.

Serdar Savaş

By

Serdar Savaş · Founder and Chairman

In the construction industry since 1989; founded Savaş Grup A.Ş. in 1998. Has led 350+ factory, hotel, residential and wellness projects in 22 countries. Writes on the urban-transformation contracting model and international project partnerships.

Urban Transformation

Frequently Asked Questions

01Who is eligible for the "Half on Us" support?
Owners of buildings in Istanbul whose risk assessment is completed by 31 December 2026. When the building is demolished and rebuilt, each dwelling receives a TRY 875,000 grant, a TRY 875,000 loan and TRY 125,000 relocation support; commercial units receive a TRY 437,500 grant.
02Is the grant repaid, and what are the loan terms?
The grant is not repaid. Loan repayment starts two years after the building permit, the term is ten years and the first year is interest-free; a low rate applies afterwards. Confirm current rates with the provincial directorate when applying.
03How is the risk assessment done and how long does it take?
A Ministry-licensed institution takes core samples and rebar readings, prepares a performance-based report and files it with the provincial directorate, which annotates the title deed. It usually takes 3–6 weeks and a single owner can apply.
04How long does urban renewal take in Istanbul overall?
From assessment to occupancy permit, 18–26 months is typical: assessment and decision 2–3 months, design and permit 2–4 months, demolition 1 month, construction 12–18 months. Fast owner decisions and an early "Half on Us" application shorten the timeline.